Contract management for new infrastructure

Report 16: 2021–22. Tabled date: 2022-05-17. 11 recommendations published as HTML.

All audit reports

Tabled Report 16: 2021–22

Tabled date
2022-05-17
Report year
2021-22

Infrastructure

Entities audited

Recommendations

  1. QAO's text Addressed to: the Department of Energy and Public Works

    strengthens its whole-of-government framework to ensure it clearly states the minimum requirements for managing infrastructure contracts and provides supporting guidelines to public sector entities in applying the framework
  2. QAO's text Addressed to: the Department of Energy and Public Works

    reviews and where necessary updates its whole-of-government framework at least every 3 years to ensure it reflects contemporary better practices and lessons learned from contract management activities.
  3. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    revise their internal policies, procedures, and guidance for managing infrastructure contracts by
    • outlining specific contract management processes and requirements to complement the government frameworks for managing infrastructure contracts.
    • clearly defining and communicating the roles and responsibilities for managing contracts
    • providing appropriate training and support to staff managing contracts
    • improving contract registers to ensure a complete record of all awarded contracts
  4. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    review their internal policies, procedures, and guidance for managing infrastructure contracts at least every 3 years to ensure they reflect contemporary better practices and lessons learned.
  5. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    strengthen their contract management by ensuring their planning is in line with the government frameworks and reflects better practice approaches
  6. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    implement clearly defined processes and procedures to ensure all contract risks and issues are identified and effectively managed
  7. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    apply standardised processes and procedures for recording, evaluating, approving, and reporting on contract variations
  8. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    implement clearly defined processes and procedures for developing project design briefs (including specifying what the contract is expected to deliver) and for undertaking stakeholder consultations during the project design stage
  9. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    assess, report, and where necessary act on contractor performance
  10. QAO's text Addressed to: the Department of Energy and Public Works and the Department of Education

    implement appropriate processes and procedures for sharing lessons learned and better practices from contract management activities.
  11. QAO's text Addressed to: all government departments

    We recommend that all government departments review their internal policies, procedures, and guidance for managing infrastructure contracts at least every 3 years and, where necessary, implement changes to enhance their contract management performance.

Authoritative report — Queensland Audit Office

Report PDF on QAO

Source: Queensland Audit Office, CC BY 4.0

Catalogue snapshot 2026-10-09

© The State of Queensland (Queensland Audit Office) 2026

Report metadata arranged into a catalogue. Recommendations reproduce QAO's words with HTML formatting simplified; no model summaries. Responses and PDF bodies are excluded.

Report pages checked individually. Recommendations and body-derived entities are withheld for licence exceptions. Images, logos and multimedia are excluded.

No endorsement by the State of Queensland or Queensland Audit Office is implied.

CC BY 4.0 · QAO copyright and exceptions